West Virginia approves 1,200 MW gas plant and solar, with financing surcharge
The November 17 decision approves proposed generation and financing-cost recovery. The utilities estimate an initial $1.18 monthly residential bill increase; the facilities are not yet operating.
By Greener Numbers Editorial Team · Published November 25, 2026 · Updated 11/25/2026
The West Virginia Public Service Commission approved Monongahela Power and Potomac Edison's application for a 1,200-megawatt combined-cycle natural gas plant and 70 MW of solar on November 17, 2026. Its official release identifies the gas-plant site as the existing Fort Martin Power Station in Monongalia County.
The commission puts the proposed gas plant's cost at $2.48 billion and the solar projects' estimated cost at $182 million. The solar sites are Valley Point near Albright, Davis adjacent to the town of Davis, and Wylie Ridge in Weirton. Approval to construct is not evidence that the facilities are already generating electricity.
The utilities also received approval for a surcharge to recover financing costs incurred during construction and after the facilities enter service, until those costs are included in base rates. The companies estimate an initial residential bill increase of about $1.18 per month, or 0.9 percent. That is an initial estimate, not a fixed lifetime charge.
FirstEnergy's November 20 Form 8-K identifies the gas project as Maidsville Energy Center and confirms the financing-cost cash-recovery provision. The filing says the order led the company to increase its 2026-2030 capital investment plan from $36 billion to $38 billion. Those are company-wide planned investments, not the gas plant's standalone construction price.
The commission says the utilities filed their application in February, citing a projected capacity shortage beginning in 2029 and continuing through 2045. It required construction-progress and cost updates in their January 2027 annual filings, along with notice at least 30 days before construction begins. Projected need is not measured future demand.
The official release points readers to Case 26-0108-E-CN. It establishes construction approval and financing-cost recovery, but does not establish that every projected large customer will connect or that the project will finish on budget. The approval date remains November 17 despite later reporting about the decision.