Latitude tracks 120 GW of signed data-center load, far below the reported pipeline

The research platform counts 537 GW of reported load across 53 utility territories. Signed agreements, energized projects and generation solicitations remain different stages, not interchangeable measures of a power shortfall.

Latitude Media published a November 13, 2026 snapshot of data-center power development using its Latitude Intelligence research platform. Across 53 utility territories tracked at launch, it counts 120 gigawatts of signed data-center load, meaning projects with executed agreements to take electric service. That is about 5.5 times the 22 GW of currently operating data-center load in the same footprint, not a census of every U.S. utility.

The platform counts 537 GW of total reported data-center load across those territories, roughly 4.5 times the signed figure. Projects in that wider pipeline have not necessarily reached an executed service agreement. Reported interest, signed demand and operating load should not be added together as if they were separate groups of completed projects, or treated as equally certain future electricity use.

Signed demand is also concentrated relative to utilities' existing systems. The article puts AEP Ohio's signed data-center load at 235% of its current peak demand, NIPSCO's at 169% and PPL's at 145%. These comparisons place future contractual demand against current utility peaks. They do not mean the new facilities are already drawing that power or establish that every project will arrive simultaneously.

For projects already energized, the platform estimates an average of 33 months from announcement to first power across 14 projects dating from late 2021. The article notes that its broader announcement-to-power sample has 19 projects and that outliers were excluded from the average. This small, selected historical sample is not a promised connection time for the much larger pipeline.

On the supply side, Latitude counts 37 GW of generation procurements open or under consideration across the six largest utilities it tracks. Examples include Dominion seeking up to 7.3 GW, Georgia Power pursuing 2-6 GW, and 4 GW solicitations each for Indiana Michigan Power and Public Service Company of Oklahoma. Those figures describe procurement activity, not completed plants, and are not a directly comparable supply total to subtract from all 120 GW of signed load.

The useful distinction is the progress between stages: an executed service agreement is not an energized data center, and a generation solicitation is not an operating power plant. The figures are the research platform's own tracked estimates, not a regulator's nationwide finding. They do not establish an imminent physical power deficit, a household bill increase or how much annual electricity the contracted facilities will ultimately consume.