ISO-NE files large-load proposal with firm and flexible service options

The grid operator proposes a $250/MWh re-dispatch threshold for non-firm loads. Application and study processes would begin June 1, 2027; the filing is not a FERC approval.

ISO New England said on November 13, 2026, that it, the New England Power Pool and the Participating Transmission Owners Administrative Committee jointly filed a large-load integration proposal with the Federal Energy Regulatory Commission this week. The grid operator says the proposal is designed to preserve bulk-power reliability and avoid shifting costs to other consumers. Those are the proposal's goals, not proof of guaranteed household bill reductions.

The proposal would establish an application and study process for proposed large loads, with implementation of that process planned for June 1, 2027. That date should not be read as an announcement that every new transmission-service provision is already approved or available. The new announcement reports a filing with FERC, not an order accepting it.

Firm contract demand service would give a customer the same priority as other firm loads. It would require new capacity and transmission-network upgrades to support the large load. Under the proposed "bring your own new capacity" requirement, the load's demand would have to be matched by new capacity supply. The operator says further stakeholder discussions on this requirement will continue in 2027.

Two non-firm pathways would offer different tradeoffs. Interim contract demand service would provide a temporary option for customers working toward firm-service requirements. Non-firm contract demand service would be a permanent option for flexible loads willing to reduce consumption under specified conditions. The latter would not require designation of new capacity supply, but the operator says it may need less extensive network upgrades, not necessarily no upgrades.

The proposal uses a $250-per-megawatt-hour local energy-price threshold to trigger re-dispatch of non-firm and interim-service customers. Re-dispatch would require reduced consumption or increased eligible generation. ISO-NE says the region currently crosses that threshold in about 1% of hours. That reported frequency is not a guarantee about future curtailment hours or the operating costs of a particular data center.

Non-firm and interim contract demand service would also be excluded from the calculation of the region's installed capacity requirement and related values. That requirement determines how much generating and demand-reducing capability is procured through the capacity market. The proposed design links lower service priority to demand flexibility; it does not make the new loads disappear from the physical grid or establish that all costs to other customers have been eliminated.