daily · Climate Policy

DOE extends Campbell emergency availability through February 12

A November 13 order begins November 15 with dispatch, reporting and environmental conditions. It extends existing plant availability without promising quantified bill savings.

A new U.S. Department of Energy emergency order directs MISO and Consumers Energy to keep Michigan's J.H. Campbell coal plant available from November 15, 2026 through February 12, 2027. Order No. 202-26-51 was issued November 13 under section 202(c) of the Federal Power Act. It extends a sequence of prior orders rather than commissioning new generating capacity.

The order identifies Campbell as a 1,420-megawatt facility in West Olive, Michigan. Its predecessor ran through November 14. DOE bases the new action on its finding of continuing regional reliability risks; that is the agency's determination, not independent proof that a particular future outage would occur without the plant.

The operative conditions require availability for emergency needs and direct MISO to employ economic dispatch only during the hours necessary to meet the emergency while minimizing ratepayer costs. They do not require round-the-clock generation or establish that electricity bills will fall by a particular amount.

MISO must notify DOE daily about compliance and provide information by November 28 on measures taken or planned to keep the plant available. Consumers must follow MISO availability and dispatch orders and file tariff revisions or waivers with FERC as needed. The order states that rate recovery is available under the governing statute; it does not give a final customer-cost allocation.

Environmental monitoring, reporting and recordkeeping obligations continue to the maximum extent feasible under emergency operation. The order does not excuse fees or required emissions offsets or allowances, and limits dispatched operation to MISO's specified times and parameters. It also says the plant must not be considered a capacity resource under this order.

The legal scope remains temporary. DOE acknowledges a September court opinion interpreting its emergency authority, says it disagrees and sought rehearing, and asserts the new order is consistent with that opinion. The document is an operative federal directive, not a final resolution of that dispute or approval for permanent operation after February 12.